How to Price a Government Contract Without Destroying Your Margin

2026-11-13

Here is the most dangerous number in your entire bid.

Not your turnover. Not your win rate. The price you type into the pricing schedule.

Because that number is not an estimate. It is a promise. If you win, you will be held to it for one year, three years, maybe five. Every wage rise, every price increase, every surprise on day one comes out of your margin, not the buyer's pocket.

Plenty of capable businesses win public sector contracts, celebrate, and then spend three years quietly losing money delivering them. The work was fine. The price was wrong.

This guide shows you how to price a government contract properly. We will build a real tender pricing example from the first pound of labour to the final line of profit, and show you what happens to that profit if you ignore inflation. Every figure is calculated, and the assumptions are listed so you can swap in your own.

UK business team building a tender price from direct costs, overheads and margin
A winning price is built from your real costs upward, not guessed downward from a competitor
4.1%
The April 2026 rise in the National Living Wage, from £12.21 to £12.71 Employer National Insurance is 15 percent above a £5,000 threshold that is frozen until 2030/31. Your labour costs move every year, whether your contract price does or not.

How Public Sector Buyers Actually Assess Price

Before you build a price, understand how it will be judged.

Under the Procurement Act 2023, contracts are awarded to the most advantageous tender, usually shortened to MAT. This replaced the old "most economically advantageous tender" wording, and the government's own guidance says it is not a change in policy. Tenders do not have to go to the cheapest bidder.

Three points from the official guidance matter to you.

The weightings are published. Buyers must tell you the relative importance of each criterion, for example quality, price and social value, before you bid. Read them first. They tell you how much a pound saved is actually worth.

Value for money is broader than cost. The guidance describes it as the optimal whole life blend of economy, efficiency and effectiveness, and says it is likely to be broader than cost alone in most procurements.

Buyers are warned about relative price scoring. Many price formulas score you against the lowest bid. The guidance tells authorities to be wary of this method and to test it, but you should still check your tender's formula, because it decides how much a price cut can gain you.

You can read the full guidance on GOV.UK.

Step One: Direct Costs

Direct costs are everything that exists because this contract exists. If the contract disappeared, so would they.

For most service contracts, labour is the biggest line, and it is where most pricing mistakes begin. Do not price on the hourly wage alone.

Employer on costs. Employer National Insurance is 15 percent on earnings above £5,000 a year, and you must pay at least the minimum employer pension contribution, currently 3 percent of qualifying earnings. Check your own scheme terms, which may be higher.

Cover. This is the cost almost every first time bidder misses. If the contract needs someone on post for 40 hours every week of the year, one employee cannot deliver it. They take holiday, and they are sometimes sick. You pay for those hours, and you still have to cover the service. In our example, one post needs about 1.15 people to deliver every hour of the year.

Everything else. Supervision, equipment, uniforms, training, checks, vehicles and consumables. List them one by one. Buyers can ask you to justify your price, so vague totals will hurt you.

Step Two: Overheads

Overheads are the costs of running the business that no single contract causes. Management, finance, HR, insurance, accreditation fees, software, office costs.

Do not pick a percentage out of the air. Work yours out. Take your total annual overheads and divide them by your total annual direct costs. That gives you a recovery rate. If you price below it on every contract, you are paying to work.

Win more contracts and that rate usually falls. Win fewer and it rises. Revisit it at least once a year.

Step Three: Contingency

Contingency is not padding. It is a deliberate allowance for risks you can name.

Write the risks down. Higher than expected absence. Equipment failure. A volume variation. A delay in handover from the outgoing supplier. Then put a sensible value against each, based on how likely it is and how much it would cost.

A flat 3 percent on direct costs is a reasonable starting point for a stable, well understood service. Raise it for uncertain scopes and unknown buildings. Lower it where the buyer has bought the risk back through the contract.

Step Four: Mobilisation

Mobilisation costs are the one off costs of starting the contract. Recruitment, TUPE consultation and transfer administration, training, uniforms, equipment, systems setup, a dedicated mobilisation lead and the time spent on site before service begins.

Evaluators score your mobilisation plan harshly, so your price must be able to afford the plan you describe. A strong plan with no money behind it is a promise you cannot keep.

Check how the pricing schedule treats these costs. If there is a separate line for mobilisation, use it. If not, spread the cost across the contract term. Never leave it out and hope it disappears.

Step Five: Contract Inflation

This is where profitable contracts quietly turn into loss making ones.

The National Living Wage rose 4.1 percent in April 2026. If your contract is fixed price and your people are paid at or near that rate, a rise like that comes straight out of your margin every year.

Before you price, find out how the contract handles price changes. Look for a price review or indexation clause, and check what it is linked to. If the tender pack does not say, raise it as a clarification question. The answer changes how you should price.

If there is no mechanism, you have two choices. Build forecast wage rises into your price, or accept that your margin will shrink each year. Choose deliberately, not by accident.

Finance and bid team reviewing a tender pricing schedule together
Pricing is a team exercise: finance, operations and the bid writer must agree every assumption
Business owner reviewing a tender pricing schedule and cost assumptions
Every line of your price should trace back to a cost you can explain

A Tender Pricing Example, Line By Line

Here is a worked example. It prices one service post delivering 40 hours a week, every week of the year, which is 2,080 service hours. Labour is paid at the April 2026 National Living Wage of £12.71 an hour.

These figures are an illustration, not a benchmark. The assumptions are ours, so replace them with your own.

Line Basis Annual cost
Gross pay per employee 2,080 paid hours at £12.71 £26,437
Employer National Insurance 15 percent above £5,000 £3,216
Employer pension 3 percent of qualifying earnings £606
Loaded cost per employee £30,258
Labour cost to cover 2,080 service hours Cover factor of 1.145, allowing 5.6 weeks holiday and one week sickness £34,657
Supervision Assumed 6 percent of labour £2,079
Equipment, uniform, training and consumables Assumed £2,000
Direct costs £38,736
Overheads Assumed 10 percent of direct costs £3,874
Contingency Assumed 3 percent of direct costs £1,162
Mobilisation £3,000 spread over three years £1,000
Total cost £44,772
Margin 8 percent of the price £3,893
Annual price £48,665

That works out at £23.40 per service hour, against a wage of £12.71. The gap is not greed. It is the real cost of delivering a reliable service.

The markup trap

Notice that the price is 8.7 percent above cost, not 8 percent. That is because margin is calculated on the price, not the cost.

If you simply add 8 percent to your cost, your price is £48,354, and your real margin is 7.41 percent. On a large contract, that quiet error is a lot of money. Decide whether your target is a margin or a markup, and use the right formula.

What Happens If You Ignore Inflation

Now take that same contract and fix the price for three years. Assume wages rise by the same 4.1 percent each year. This is an illustration, not a forecast. All other costs are held flat to keep it simple.

Year Total cost Profit at the fixed price Margin
1 £44,772 £3,893 8.0 percent
2 £46,527 £2,139 4.4 percent
3 £48,354 £312 0.6 percent

You priced for an 8 percent margin. By year three you earn £312 on a contract worth nearly £49,000 a year, and one bad month turns it into a loss. Nothing went wrong operationally. The price simply did not survive contact with the calendar.

Quality Versus Price: Do Not Race To The Bottom

The next temptation is to cut your price to win. Run the numbers first.

Suppose a tender weights quality at 60 percent, social value at 10 percent and price at 30 percent. Price is scored by dividing the lowest price by yours, then multiplying by 30. Quality and social value are scored out of five.

Bidder A Bidder B
Price £100 (lowest) £110
Price score 30.0 27.3
Quality score 3 out of 5, giving 36.0 4 out of 5, giving 48.0
Social value score 3 out of 5, giving 6.0 4 out of 5, giving 8.0
Total 72.0 83.3

Bidder B charges 10 percent more and wins comfortably. Every tender formula is different, so check yours, but the pattern holds wherever quality carries real weight. A stronger written response is often worth far more than a lower price, and it does not cost you margin.

The danger of pricing too low

There is a second risk. The Procurement Act 2023, in section 19, lets a buyer treat a tender as abnormally low. The guidance says the buyer must notify you and give you a reasonable opportunity to demonstrate that you can deliver at the price offered. If you cannot, they may disregard your tender.

So keep a price justification file for every bid. Your cost build up, your assumptions and your delivery plan. If a buyer asks, you can answer in hours, not days. And even if nobody asks, the same file protects you from underpricing in the first place.

Confident business owner who has priced a tender with a protected margin
Know your floor price before you start negotiating with yourself

The cheapest bid does not win the contract. The best scoring bid does, and the best scoring bid is the one you can still afford to deliver in year three.

Your Tender Pricing Checklist

✓Read the published weightings and price scoring formula before you start
✓Build labour from loaded cost, including employer National Insurance, pension and cover
✓Calculate your own overhead recovery rate from real figures
✓Name your risks and value your contingency against them
✓Cost the mobilisation plan you actually described in your quality answers
✓Ask in clarifications how price changes and wage rises are handled
✓Test your margin in years two and three, not just year one
✓Check you are calculating margin on price, not markup on cost
✓Keep a price justification file in case a buyer questions an abnormally low price
✓Have someone outside the pricing team check the maths before submission

Price To Win, And Price To Keep What You Win

The goal is not the lowest price or the highest score. It is a price that wins the contract and still leaves you a business at the end of it.

Build it from the bottom up. Test it against inflation. Check it against the scoring formula. And protect it with a file that proves every number.

This article is general guidance. The figures are illustrative, based on published employment cost rates from April 2026, and your own costs, contract terms and tax position will differ. Check current rates and take financial advice before you submit a price.

Not sure your bid price protects your margin?

Send us your draft pricing and the tender weightings, and we will test it against your costs, inflation and the scoring formula, and tell you honestly where it is exposed. No obligation. No sales pitch.

Request a free tender pricing review

+44 20 7078 8487

info@synergysolutionsglobal.co.uk

We Solve. You Win.

Need help with a bid or facilities challenge?

Send a request and we will advise on the most suitable next step.

Request Support

© 2026 Synergy Solutions Global Ltd. All rights reserved.